Preliminaries in a BOQ: How I Use AI to Check Nothing Is Missing

TechCurrent-News
0
Bill of quantities preliminaries section with a checklist on a quantity surveyor desk

Preliminaries are the part of a bill of quantities that nobody wants to measure. There is no drawing to count from, no wall to take off. Yet this section routinely holds 10 to 15 percent of the contract sum, and when it is wrong, the contractor either loses money quietly or claims it back loudly.

I now run every preliminaries section through an AI checklist pass before the BOQ goes out. The AI does not price anything. It tells me what is missing, what contradicts the specification, and what is described too loosely to hold up in a dispute. Here is how I do it.

1. Why preliminaries go wrong

Preliminaries are copied from the last job and lightly edited. That is the problem. A site with a tower crane, a tight urban access road and a night-work restriction needs a very different section from a suburban low-rise, but the copied template often looks the same. The errors are rarely typos. They are leftover items that do not apply and missing items that do.

2. Feed it the real constraints, not just the template

I paste three things into the prompt: the draft preliminaries, the site constraints from the tender documents (access, working hours, neighbours, utilities, security), and the contract conditions summary. Then I ask:

“Compare these preliminaries against the site constraints and contract conditions. List items that appear necessary but are not included, items included that seem irrelevant to this site, and any description that is vague about duration, quantity or responsibility. Do not suggest prices.”

The “do not suggest prices” line matters. Without it, the AI drifts into invented rates, which I never want in a first pass.

3. Time-related versus fixed items

The most useful split in preliminaries is between fixed items (set up, mobilisation, final clean) and time-related items (site management, scaffolding hire, temporary power, security). A time-related item priced as a lump sum hides the extension-of-time cost. I ask the AI to sort every line into one of the two groups and flag any time-related line that has no stated duration.

This sorting alone has caught lines that would have cost real money in a delay claim. If the item runs per week, the BOQ should say per week.

4. Check the wording for who does what

Responsibility gaps are where disputes start. “Provide temporary water” does not say who pays the connection, the meter, or the usage. I ask the AI to highlight every line where the responsible party, the extent, or the standard is not stated. I then decide which gaps to close in the BOQ and which belong in the specification.

5. A short checklist I keep for the final read

  • Every time-related item has a duration or a rate basis.
  • Site-specific constraints are each answered by at least one line.
  • No leftover items from the previous project (names, locations, systems).
  • Insurances, bonds and statutory fees match the contract conditions.
  • Provisional sums are described well enough to be valued later.

What the AI never decides

It does not know your client, your contractor’s likely method, or what the site visit showed. It cannot tell that the access road is narrower than the drawings suggest. Every item it flags is a question for me, and every item it misses is still my responsibility. I also keep real project names and figures out of what I paste into public tools, and replace them with neutral placeholders.

The result

The pass takes about fifteen minutes. It does not replace a careful read, but it makes that read faster and more focused. On the last few tenders it has surfaced two to four issues each time that I would otherwise have found at the clarification stage, or not at all.

If you only change one habit, make it this: stop copying preliminaries unchecked, and make every line answer a real constraint of the project in front of you.